Civil Contractor of Choice

PROJECT DETAILS

CLIENT: RailCorp

LOCATION: Gosford, NSW

VALUE: $5.1m

DURATION: 10 months

Gosford Stabling Yard

Scope of work

  • Construction of three railway maintenance sidings track formation with concrete walkways
  • Construction of amenities and decant facilities
  • Services installation; stormwater, sewer vacuum system and electrical lighting
  • Retaining wall and shotcrete wall construction
  • Construction of train buffer stop structures
  • Construction of carpark, retaining blockwall and landscaped areas
  • Construction of security fencing
  • High voltage power connection and sub-station works

Project highlights

  • Meeting Railcorp's stringent milestones for trackwork and overhead power installation

< Back