PROJECT DETAILS
CLIENT: Australian Rail Track Corporation (TEJV Alliance)
LOCATION: Ulan, Hunter and North Coast Lines, NSW
VALUE: $25.8m
DURATION: Various packages over a 30 month period
ARTC Northern Improvement Alliance
Scope of work
- Civil works undertaken at 21 rail crossing loops
- Bulk earthworks and track formation construction
- Drainage including new and existing culvert extensions
- Construction of new rail under bridges and over bridges
Project highlights
-
Robson established themselves as preferred Civil Contractor to Transport Express JV (TEJV)
- Re-establishment of a dormant quarry close to the Ulan Line Crossing Loops and utilisation of Robson mobile crushing and screening plant enabled significant savings in the cost of imported materials.
- Extensive knowledge of the Hunter Valley Rail Network and HV Coal Supply Chain enabled Robson to provide valuable input to project planning and delivery.
- Consultation with local landowners and community liaison
provided accelerated start on various packages